How PepsiCo is reducing carbon emissions through industrial electrification

How can food manufacturers reduce carbon emissions? PepsiCo's potato chip plant combines industrial electrification and thermal storage to support net-zero manufacturing without disrupting production.
People inspecting a potato field as part of sustainable food manufacturing in the Netherlands

Project facts

Client
PepsiCo
Location
Noord-Holland, The Netherlands
Date
2024 - 2026
Challenge
Implement structures and site adjustments to enable industrial electrification and support PepsiCo's decarbonisation ambitions while maintaining production.
Solution
Worked closely with the on-site operational team and stakeholders to prepare the existing factory for industrial electrification and thermal energy storage without interrupting production.

PepsiCo is aiming to achieve net-zero emissions by 2050 or sooner. As part of  its Climate Transition Plan, PepsiCo is transitioning from natural gas to electrical power at its potato chip production plant in Broek op Langedijk. This project is the first industrial electrification project with high temperature storage in the Netherlands. It is expected to reduce CO2 emissions at the plant by more than 50% and, ultimately, by as much as 98%.

Why net-zero manufacturing requires new heat solutions

One of the challenges for electrifying industrial sites is making a business case in an environment where electricity costs can be high. This is where a combination of electrical heaters and high-temperature thermal storage comes in. It enables heat to be produced and stored when electricity costs are favourable. It’s an innovative solution developed by sustainable energy company Eneco in partnership with PepsiCo. Hot air produced by an electrical heater is passed through a large container of iron slag-based material which retains heat. When required, the stored heat is transferred to PepsiCo’s thermal oil system.

One of PepsiCo’s requirements from the electrification solution was that it should not impact the potato chip production process. “We wanted to decarbonise but we didn’t want to change the way we operate - the way we fry our potatoes,” said Geert Jan Euverman, Senior Category Manager for Procurement Energy and Waste Management EMEA at PepsiCo. 

He added that during the development phase the company had minimised involvement from the team at Broek op Langedijk so they could continue to focus on their core business running the plant. 

This meant that when it came to preparing the production site for electrification and thermal storage, it was important to ensure the plans worked on the ground and that the project was embraced locally. This is where Haskoning came in.

Integrating thermal storage technology into existing plants

It's a beautiful project, producing potato chips more sustainably, and it required a major transformation to make it possible

PepsiCo contracted us to prepare the local site for the transformation. Besides constructing new buildings, we installed a new potato conveyor system throughout the factory and relocated several key functions, including the potato intake area. It was like performing open-heart surgery on a live production site. We had to relocate essential operations without interrupting production.

Coen ter BergProject Manager at Haskoning
The electrification project is being introduced at the oldest potato chip factory on mainland  Europe. With a constrained site area and no greenfield available, this involved careful planning. Timing was critical too - the team had eight months to realise a programme of sequential projects to make room for the power-to-heat building and thermal oil system modifications.

We were looking for a combination of things

First, resources – they need to be knowledgeable so they know the questions to ask, can go back to their organisation to get the right expertise on the table and have the right capabilities to organise what needs to be done. We required people who can integrate well. What was special was how Haskoning became part of the project team, the right hand of our engineering manager.

 

Geert Jan EuvermanSenior Category Manager for Procurement Energy and Waste Management EMEA at PepsiCo
Senior Category Manager for Procurement Energy and Waste Management EMEA at PepsiCo

Stakeholder collaboration as a key success factor

Coordinating with the local team was essential to understand how to implement changes without interrupting local processes. 

We developed a strong working relationship where we really became one team, all committed to the success of the project

Everything we did needed to work not just for the electrification process but operationally too. This is why it was so important we were aligned and that the local team took ownership and embraced the transformation.

 

Coen ter BergProject Manager at Haskoning

Get in touch

Looking to reduce carbon emissions without disrupting production? Let's discuss your challenge.

Coen ter Berg - Project Manager, Industry & Buildings

Coenter Berg

Project Manager, Industry & Buildings

Always up-to-date on latest industry insights?

Sign up for our newsletter and always be up to speed on the latest Industry trends and innovations
Two men in a manufacturing factory looking at a product belt discussing how to optimise their operations with industrial engineering and manufacturing services.